09-05-20, 09:30 AM | #1 |
Uber EcoRenovator
Join Date: Apr 2011
Location: Strathroy Ontario Canada
Posts: 657
Thanks: 9
Thanked 191 Times in 129 Posts
|
Or
The Grid will not allow a connection. I had applied 3 times with descending solar outputs 10kw, 6kw, and 2kw Sorry in-eligible!! due to power constraints. Micro fit or net meter. DENIED Randen |
09-05-20, 09:59 AM | #2 |
Journeyman EcoRenovator
Join Date: Jun 2013
Location: Delhi, NY
Posts: 332
Thanks: 20
Thanked 53 Times in 40 Posts
|
The grid or your provider? Is it a technical problem or a political one?
|
|
|