12-11-14, 11:27 AM | #21 |
Administrator
Join Date: Aug 2008
Location: Germantown, WI
Posts: 5,525
Thanks: 1,162
Thanked 374 Times in 305 Posts
|
*poke* for pics!
__________________
Current project - To view links or images in signatures your post count must be 0 or greater. You currently have 0 posts. To view links or images in signatures your post count must be 0 or greater. You currently have 0 posts. & To view links or images in signatures your post count must be 0 or greater. You currently have 0 posts. |
12-11-14, 11:50 AM | #22 |
Super Moderator
Join Date: Jun 2013
Location: SC
Posts: 2,923
Thanks: 172
Thanked 564 Times in 463 Posts
|
I will second the picture request. This building method is very interesting.
|
12-11-14, 06:54 PM | #23 |
Steve Hull
Join Date: Dec 2012
Location: hilly, tree covered Arcadia, OK USA
Posts: 826
Thanks: 241
Thanked 165 Times in 123 Posts
|
OK, OK. . . I will figure out how to get the pictures on the cell phone transferred. Latest is that over head shop lights are installed, outside stained and overhead doors/windows installed.
Got an interesting mosquito borne tropical virus while in Puerto Rico several weeks back and that has slowed me down (chikugunya). Sadly, lots of muscle aches and a long time for full recovery. Not whining and still working like I always do on the farm (and now shop) but it has made me think . . . . Steve
__________________
consulting on geothermal heating/cooling & rational energy use since 1990 |
12-12-14, 04:32 PM | #24 |
a van down by the river
Join Date: Jun 2011
Location: Kaukauna,WI
Posts: 108
Thanks: 6
Thanked 5 Times in 5 Posts
|
Any worry about moisture and the OSB on the sips? I would worry about water wicking up the edges of the OSB in a shed environment
Post pics please we are interested
__________________
Gary R “If you want total security, go to prison. There you're fed, clothed, given medical care and so on. The only thing lacking... is freedom. ” ― Dwight D. Eisenhower |
12-12-14, 06:17 PM | #25 | |
Apprentice EcoRenovator
Join Date: Oct 2014
Location: SE MI
Posts: 105
Thanks: 3
Thanked 12 Times in 9 Posts
|
Quote:
|
|
12-13-14, 10:50 PM | #26 |
Supreme EcoRenovator
Join Date: Mar 2009
Location: Portland, OR
Posts: 4,004
Thanks: 303
Thanked 723 Times in 534 Posts
|
Edge Gluing to OSB vs. Tornado Alley
SH,
This roof-wall attachment looks a bit flakey to me... You are anchoring your roof to a 2 x 6-ish that has its edges glued to OSB?? Really? Glued to OSB?? I looked up Arcadia, OK map and here's what I got: Then I Goggled "Tornado Alley Map", and here's what I got: SH, is my imagination, or is Arcadia at the very heart of Tornado Alley? With global weather changing, the tornadoes could get even stronger and more frequent? What are the chances? Maybe Tornado Alley will move to Texas, where it belongs, and just leave Oklahoma alone. Oh, it's already in Texas... -AC
__________________
I'm not an HVAC technician. In fact, I'm barely even a hacker... |
12-14-14, 06:07 AM | #27 |
Steve Hull
Join Date: Dec 2012
Location: hilly, tree covered Arcadia, OK USA
Posts: 826
Thanks: 241
Thanked 165 Times in 123 Posts
|
AC,
The connection of the wall to the roof is done with the aid of 2x6 trusses. Furthermore, I used steel strapping screwed on the truss top and then down the side of the wall (each two feet). I also used J bolts in the concrete on 4 foot centers (code 10 feet) to additionally prevent lift. The schematic that was posed on SIP construction is only one of many that are out there. I choose to add in strapping, extra point nailing, and far more construction adhesive than was called for. Then on the exterior, I put on plywood and 2 inch vertical battens every foot to further hold the plywood on. That further strengthens the exterior. As for tornados. Every region has weather issues and these really scared me when we first moved here some 30 years ago. The risk is NOT tornados as the likelihood of a given sq mile being hit is once every 400 years. Rather, it is ice storms and those don't excite people like a whirling tornado. Took a lot of photos yesterday. Now I will get daughter to help me transfer them from phone to computer and then from computer to here. Had to laugh as the first photos have green leaves on the trees! Steve
__________________
consulting on geothermal heating/cooling & rational energy use since 1990 |
12-14-14, 08:43 AM | #28 | |||
Apprentice EcoRenovator
Join Date: Oct 2014
Location: SE MI
Posts: 105
Thanks: 3
Thanked 12 Times in 9 Posts
|
Quote:
Quote:
Quote:
What I always want to know is how do the carpenters shoot those long screws perpendicular to the roof deck in 2 planes ? Last edited by theoldwizard1; 12-14-14 at 08:52 AM.. |
|||
12-14-14, 10:43 AM | #29 |
Steve Hull
Join Date: Dec 2012
Location: hilly, tree covered Arcadia, OK USA
Posts: 826
Thanks: 241
Thanked 165 Times in 123 Posts
|
Old wizard,
I too was amazed that ~ 2000 9 inch crews were used to screw down the 7 inch roof SIP panels into the trusses and only three missed the trusses! And those only by 1/8 th inch. They struck a chalk line on the roof decking as they put up the panels, but they were careful to drive in the screws exactly perpendicular in both directions. This is where I had help from a contractor that, before this job, had never used SIPS. He was amazed at the strength, quickness of putting it up and how straight and true everything was. He says he will not ever build a "stick" wall again. Forgot who asked, but this 5/8 inch oriented strand board (OSB) on either side of the SIPS is not the stuff you get at big box stores. Rather, it is far more stable in the presence of water and actually can be left out in open conditions (rain, snow, etc) for 6 months with no degradation. It looks like a resin or something is in it. Steve
__________________
consulting on geothermal heating/cooling & rational energy use since 1990 |
12-14-14, 10:53 AM | #30 | |
Apprentice EcoRenovator
Join Date: Oct 2014
Location: SE MI
Posts: 105
Thanks: 3
Thanked 12 Times in 9 Posts
|
Quote:
You may have mentioned it, but I will ask again. How were the wall sections connected ? Some designs use standard 2by for the spline, some use OSB strips that just slip in a slot just behind the inner and outer OSB (no cold spot from the 2by). |
|
Tags |