PS
PV system passed inspection and is up and running. Just waiting for NW Energy to install the net meter so I get credit for the power. We had 22 inches(!) of snow over the last two days, so I guess I finished just in time

Nice! Congrads on passing. Sorry to hear about the snow!

I've been looking at the Enphase products for about a year and just recently
seen they have come out with a unit that handles 2 panels!

I'm wondering if you also got the network-connect unit too?

~~~
My meter, seen here:
http://ecorenovator.org/forum/conser....html#post4759

And some others that I've heard about, work like a KillaWatt, where direction of the current isn't detected.
I think it might be an option with my model, but not installed.

So, If I hooked up some Enphase units, my meter wouldn't 'spin backwards'..
But it would register the PV power as used, and I would be billed for
the PV produced power, like I had actually used it!
LOL! Not only giving it away for free! But being billed for it too!

I hope you don't have one of these type of meters!