The world slows down, but construction continues! Framing has been completed. The shed wall isn't exactly plumb, but it's level. Good enough! I siliconed (black silicone) the wood to keep moisture out on back side. Next is the 1" polyiso board (staggered). Then pine 3/4"x 1.5"s to finish the glazing support. Glazing support is set back 1/2" to allow the polycarbonate to be siliconed on the outside. I put 2" strips of polyiso on the inside edge of the frame to finish up the insulation. Currently working on putting up the 1/2" OSB panels over the polyiso. All the piping/ collector fins will be eventually stapled to the OSB.

The underground insulated pex I got is the reflexive bubble wrap inside of drain tile style. Some online sources point out they can lose a ton of heat if water gets into the pipe. Does anyone have experience with wood boiler pipe like this? I was thinking I might install sock drain tile pipe beneath it just incase the pipe ever got punctured to keep it dry enough. Possibly a drain hole at the low point of the underground boiler pipe just to give the water an escape route in case water ever did get in?




















Attached Images
          

Last edited by Daox; 04-05-20 at 10:34 AM..
menaus2 is offline   Reply With Quote
The Following 2 Users Say Thank You to menaus2 For This Useful Post:
Daox (04-05-20), jeff5may (04-05-20)