The cabin rough framing might be finished this weekend. I've been busy with work while my carpenter has been working away at it. Improvised design changes... I added a gable to the south facing roof line to gain more usable space upstairs. Living space should be closer to 1200 sqft. I'm using a composting toilet system not yet installed. Upstairs water closet now planned after staying in a similar sized cabin with 4 women. Off grid solar dream has moved to grid tie, way cheaper and practical for my set up. Roof, windows and insulation time coming up! Unfortunately my casual free time has about dissolved, and I'm about to stay really busy until October. Progress will come to a screeching halt by the end of May.